Key Takeaways:
- The new stadium, named Generali Stadium was unveiled today at Sforza Castle, featuring an oval design next to the current Giuseppe Meazza
- Generali will hold naming rights for 20 years at a total cost of 650 million euros, with construction slated to begin in the second half of 2027 and conclude by the end of 2031
- The facility’s capacity will be 71,500 seats, including two 11,500-seat end stands with a 37-degree incline inspired by Borussia Dortmund’s “Yellow Wall”
Comprehensive Stadium Project Revealed in Milan
AC Milan and Inter jointly revealed plans for their new home, the Generali Stadium at an event held at Sforza Castle. The modern venue, positioned adjacent to the existing Giuseppe Meazza is designed in an oval configuration, marking a major architectural departure from the current three-tier, rectangular stadium.
Naming Rights and Financial Details
The stadium’s official name, Generali Stadium is the result of a significant partnership with the insurance company Generali, which has secured the naming rights for the next 20 years by committing 650 million euros. This commercial agreement underscores the project’s scale and ambition.
🚨🏟️ OFFICIAL: AC Milan and Inter unveil new Generali Stadium from season 2031/32!
San Siro will be demolished according to current plan.
The two clubs will both build new stadium with the naming rights sold to Generali until 2052 for €650M. https://t.co/ET12egYK2J
— Fabrizio Romano (@FabrizioRomano) October 29, 2026
Construction Timeline and Demolition Plans
Building work is scheduled to commence during the latter half of 2027, with a targeted completion by the end of 2031. The timeline is driven by the aim to host matches for Euro 2032 at the new arena. During the construction period, both Milanese clubs will continue to play at San Siro. Following the move to the new venue, San Siro – formally the Giuseppe Meazza – is expected to be largely demolished, retaining only one of its iconic towers.
Design Features and Spectator Experience
The new venue will accommodate a total of 71,500 spectators across two main tiers, embracing a unique oval shape. Notably, the two end stands will each hold 11,500 seats and feature a 37-degree incline, drawing inspiration from Borussia Dortmund’s famed “Yellow Wall” to enhance the matchday atmosphere. This is a notable evolution from the current 75,000-capacity Giuseppe Meazza which features a rectangular layout with three levels.
| Stadium | Shape | Capacity | Main Features | Naming Rights Value | Construction Timeline |
|---|---|---|---|---|---|
| Generali Stadium | Oval | 71,500 | Two tiers, 11,500-seat end stands, 37-degree incline | 650 million euros (20 years) | 2027 (second half) – 2031 (end) |
| Giuseppe Meazza (San Siro) | Rectangular | 75,000 | Three levels | N/A | To be largely demolished post-2031 (one tower to remain) |